Cleans up nicely.

warning: Illegal string offset 'files' in /home/public/modules/upload/upload.module on line 481.

We're finally moving on to finish work. Just a few more days of subcontractors taking care of final wiring issues. Case work is in production and will be on site next week, and furniture is arriving now. Intelligentsia will have folks down to help with machine installation and training the first and second week of April.

We're shooting for a soft opening the week of April 12, with a "grand opening" of April 19...

As a point of reference, here's the "before" shot: